Quick Answer
To build an addition on piers, get a permit and engineered plans, then lay out the footprint, dig pier holes below your local frost line, and pour concrete footings and piers with anchor hardware. Set beams on the piers, frame the floor with joists tied to the house with a flashed ledger or a separate beam, then frame walls and roof, and enclose the crawl space.
Key Takeaways
- Pier foundations use less concrete and excavation than full basements or slabs and suit sloped lots.
- Footings must sit on undisturbed soil below the frost line set by your local building department.
- Pier size, spacing and beam size come from the engineer or code span tables, not guesswork.
- The connection to the existing house is the most critical detail for leaks and movement.
- Plan crawl-space ventilation or encapsulation, insulation and skirting from the start.
A pier foundation supports an addition on a grid of concrete columns instead of a continuous wall or slab. It is a common choice for sunrooms, bedroom bump-outs and additions on sloped or wooded lots. This guide explains how the system works, the build sequence, and the points where you need an engineer, inspector or licensed contractor.

What Is a Pier Foundation for a Home Addition?
A pier foundation is a series of concrete footings with columns (piers) rising above grade. Wood or steel beams sit on top of the piers, and floor joists span between the beams. The space underneath becomes a crawl space. Because loads go straight down through each pier, footing size and soil bearing capacity matter a great deal.
| Foundation type | Best for | Pros | Cons |
|---|---|---|---|
| Pier and beam | Sloped lots, sunrooms, small additions | Less digging and concrete, crawl-space access to utilities | Needs skirting, insulation and moisture control |
| Concrete slab | Flat lots, mild climates | Fast, low-maintenance floor | Hard to run plumbing later; needs a flat site |
| Crawl space with stem walls | Matching an existing crawl space | Continuous support, easier to seal | More excavation and concrete |
| Full basement | Adding living or storage space below | Maximum space | Most expensive and disruptive |
| Helical piles | Poor soils, limited access | Installed by machine, load-tested | Requires a specialty contractor |
Do You Need a Permit to Build an Addition on Piers?
Almost certainly. Home additions require a building permit in nearly every U.S. jurisdiction, with inspections of footing holes before concrete, framing, and final work. Many building departments also require stamped structural drawings for additions, plus zoning approval for setbacks and lot coverage. Contact your local building department before you design anything.
What Do You Need to Build a Pier Foundation?

- Plans: architectural and structural drawings showing pier size, spacing, footing depth, beam and joist sizes.
- Layout tools: batter boards, mason’s line, tape measures, line level or laser level, spray paint.
- Excavation: post-hole digger, auger (manual or towable), shovels.
- Concrete: footing forms or round fiber tube forms, rebar per plans, bagged or ready-mix concrete, anchor bolts or post bases.
- Framing: pressure-treated beams or built-up girders, joists, joist hangers, structural screws or bolts, flashing.
- Safety gear: gloves, eye protection, hearing protection, dust mask and sturdy boots.
How to Build an Addition on Piers
Step 1: Get Plans and a Permit
Work with an architect, designer or engineer to produce drawings that meet your local code. Submit them for a building permit and zoning review. Call 811 at least a few business days before digging so utility lines are marked.
Step 2: Check Soil and Frost Depth
Ask the building department for the required frost depth and the assumed soil bearing capacity. Weak, expansive or filled soils may require a soil test and larger footings or a different foundation system. The engineer uses this to size each footing.
Step 3: Lay Out the Footprint
Set batter boards beyond each corner and stretch mason’s lines to mark the outside of the addition. Square the layout using the 3-4-5 method or by measuring equal diagonals. Mark each pier center with paint where the lines cross per the plan.
Step 4: Dig the Pier Holes
Dig each hole to the depth on the plans, below the frost line and onto firm, undisturbed soil. Make the bottom wide enough for the footing size specified. Schedule the footing inspection before placing any concrete.
Step 5: Pour Footings and Piers
Place rebar as drawn, pour the footing, then set and brace round tube forms or block piers on top. Fill with concrete, consolidate it, and set anchor bolts or post bases at the exact height and position. Let the concrete cure as directed before loading it.
Step 6: Set the Beams
Fasten beams to the pier hardware, checking that they are level and in line. Use pressure-treated lumber rated for ground contact where required, or steel beams if specified. Shim only with approved materials such as steel shims, never wood scraps.
Step 7: Frame the Floor and Tie Into the House
Install joists across the beams at the spacing on the plans, usually 16 inches on center. Where the addition meets the house, either attach a ledger board with structural fasteners and proper flashing, or support the joists on a beam with its own piers, as the engineer specifies. Add subfloor glued and screwed to the joists.
Step 8: Frame, Dry In and Enclose the Crawl Space
Frame the walls and roof, tie the roof into the existing house, and get the structure weathertight with sheathing, house wrap, windows and roofing. Then insulate the floor, install a vapor retarder on the ground, and enclose the perimeter with skirting, vents or a sealed crawl-space system as your code and climate require.

Tip: Match the new floor height to the existing house before pouring piers. Measure from the existing finished floor down to determine beam and joist heights, allowing for subfloor and flooring thickness so the transition is flush.
How Deep and Far Apart Should Piers Be?
Depth is set by your local frost line and soil conditions. In warm climates footings may be fairly shallow; in cold northern regions they can need to go several feet deep. The International Residential Code requires footings to extend at least 12 inches below undisturbed ground, and deeper where frost depth requires it.
Spacing depends on the beam size and the load. Residential piers are often spaced roughly 6 to 8 feet apart under beams, but your plans or the code span tables govern the actual spacing. Heavier loads, such as bearing walls, bathtubs and roof point loads, need extra piers.
How Do You Connect an Addition to the Existing House?
This is where most problems start. A ledger must be fastened to the house rim joist (not just siding or brick veneer) with code-approved fasteners and flashed so water cannot get behind it. Because the new piers and the old foundation may settle differently, some designs use a separate beam on piers next to the house instead of a ledger, with a flexible joint and flashing between the structures.
Safety: Excavation near existing foundations, cutting openings in load-bearing walls and tying roofs together are structural work. Have a licensed engineer specify headers and connections, and hire licensed electricians and plumbers for new circuits and piping.
Common Mistakes When Building on Piers

- Placing footings on fill or above the frost line, causing heaving or settling.
- Skipping the footing inspection and pouring concrete early.
- Undersized beams or too few piers under concentrated loads.
- Poor ledger flashing that rots the house rim joist.
- Leaving the crawl space open and uninsulated, leading to cold floors and frozen pipes.
- Ignoring drainage; grade the soil away from the addition and extend downspouts.
Good drainage protects any foundation; see our guide on unclogging an underground gutter drain pipe. If you are adding space with a lighter project, read how to enclose a porch first, which can be a simpler route to an extra room.
When Should You Hire a Contractor?
Experienced DIYers often handle layout, digging and framing under permit, but most homeowners hire a general contractor or at least a structural engineer and concrete crew. Hire professionals if the site has poor soils, steep slopes, a high water table, or if the addition includes plumbing, gas or a second story.
Frequently Asked Questions
Is a pier foundation good for a home addition?
It can be. Pier and beam foundations work well for small additions, sunrooms and sloped lots because they need less excavation and concrete. They require careful moisture control, insulation and skirting, and the design must handle concentrated loads. An engineer can confirm whether it suits your soil and climate.
How deep do piers need to be for an addition?
Piers must rest on footings below your local frost line and on firm, undisturbed soil. The International Residential Code requires at least 12 inches below undisturbed ground, and cold climates require much deeper footings. Your building department sets the exact frost depth.
Can I build an addition on piers myself?
Experienced DIYers can do layout, digging and framing under a permit, but the design should come from an engineer or designer, and inspections are required. Most homeowners hire pros for concrete, structural tie-ins, roofing connections, electrical and plumbing.
How do you attach a pier addition to an existing house?
Either fasten a ledger to the house rim joist with code-approved structural fasteners and flashing, or support the new floor on a separate beam and piers next to the house. The engineer chooses the method based on loads and how much the two structures might move relative to each other.
Do pier foundations need skirting?
Most do. Skirting keeps animals out, reduces wind under the floor and helps protect plumbing from freezing. Combine it with floor insulation, a ground vapor retarder and ventilation or a sealed crawl-space system, as your local code and climate require.